Lot 5

8/18/2010 - carpet, electrical and doors installed.

8/18/2010 - All plumbing fixtures installed.

8/18/2010 - all hardware installed

8/18/2010 - kitchen island / sink area complete.

8/18/2010 - carpet installed

8/18/2010 - 3rd bath vanity completed.

 

8/18/2010 - 3rd bath shower completed

8/18/2010 - all lights and fans installed

8/18/2010 - master shower and tub area completed.

8/4/2010 - kitchen sink installed.

8/4/2010 - kitchen granite installed. They are still working on this, not completed.

8/4/2010 - master shower area

8/4/2010 - master tub area

8/4/2010 - master vanity counter, sinks and mirror installed.

8/4/2010 - 3rd hall bath - shower area tiled.

8/4/2010 - 3rd hall bath - counter top tiled and backsplash installed.

8/4/2010 - 2nd hall bath counter top and sink installed.

8/4/2010 - additional back patio - concrete poured.

8/4/2010 - additional side drive - concrete poured

8/4/2010 - landscaping completed.

8/4/2010 - landscaping completed

7/29/2010 - front door painted

7/29/2010 - backyard has been graded.

7/29/2010 - getting ready to pour additional back patio

7/29/2010 - they have started the landscaping

7/21/2010 - doors and trim have been painted.

7/14/2010 - floor tile and kitchen cabinets installed, view from breakfast/dining area.

7/14/2010 - floor tile and kitchen cabinets installed.

7/14/2010 - sidewalk and driveway poured - view from front door.

7/14/2010 - they have started installing the trim and baseboards

7/14/10 - roofing almost completed, driveway and sidewalk poured

7/6/2010 - inside walls have been textured.

7/6/2010 - they should be finsihing up the roofing and front exterior soon.

6/29/2010 - exterior stucco color has been applied.

6/29/2010 - house has been sheetrocked

6/22/2010 - beginning the stucco process

6/22/2010 - beginning the stucco process.

6/16/2010 - shingles loaded on roof, pre-stucco work has started on exterior.

6/16/2010 - HVAC installed

6/16/2010 - plumbing and electrical have been installed

6/8/2010 - house frammed

6/8/2010 - shingles have been delivered to lot and will be loaded onto roof shortly.

 

6/8/2010 - HVAC equipment has been delivered to house and will be installed any day!

5/25/2010 - footing hs been poured. floor is next :)

5/25/2010 - electrical box installed. Underground wiring and plumbing have been run

5/19 - fotting dug, preparing to be poured

5/19/2010 - footings dug, preparing to be poured

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.